Energy: First feeder for liquefied natural gas in Wilhelmshaven ready

Energy: First feeder for liquefied natural gas in Wilhelmshaven ready

In the energy crisis, the federal government has so far lacked the infrastructure to absorb liquefied natural gas (LNG). In the meantime, the situation has improved: on Tuesday, the first pier was opened in Wilhelmshaven.

The first feeder for liquefied natural gas (LNG) in Germany has been completed and opened on Tuesday. In about a month, a loaded special ship, a so-called floating storage and regasification facility (FSRU), is to dock at the landing site.

This emerges from a statement published on Tuesday by Niedersachsen Ports, a port operator owned by the state. Niedersachsen Ports had the pier built. Tankers with LNG should then arrive in Wilhelmshaven from mid-January.

“The early decision to choose Wilhelmshaven as a hub for LNG imports was correct,” said Lower Saxony’s Economics Minister Olaf Lies (SPD) at the opening.

Lower Saxony’s Environment Minister, Christian Meyer (Greens), said the new investor would contribute to security of supply in Lower Saxony and in Germany. However, he wants to reduce imports of fossil fuels, including natural gas. “The aim is to switch to climate-neutral green gases as quickly as possible and to make Wilhelmshaven the hub for green hydrogen and the import of renewable energies from the North Sea,” said Meyer.

Construction work on the landing site began in May of this year. Another FSRU in Wilhelmshaven is scheduled to go into operation at the end of 2023. As the Lower Saxony Ministry of the Environment made clear in a statement on Monday evening, there should be no more than two of the special ships at the site. Instead, an onshore terminal is to be built to replace an FSRU.

Source: Stern