River announced reforms in the Monumental for US$40 million

River announced reforms in the Monumental for US million

The estimated duration will be 27 months in two stages and the first one will run from next month until February 2023.with a request for $25 million that will be generated with the commercial agreement of the “naming right”.

In this regard, the agreement will be with the commercial firm Chango More of supermarkets and therefore after the approval of the partners both in the board of directors and in the assembly, the Monumental it will be renamed “More Monumental” or “More Monumental”.

“The general project only had one critical stage, that of the field of play, the other two will not imply that there is a change or exit from the stadium, there will be no harm to the partners, we are happy because it is the stadium we all dream of”analyzed Brito.

While adding: “The goal is for it to be finished in June 2024 with the end of work on all the issues of the new areas, the garages, the boxes, the restaurant and all the reforms that were planned.”

For his part, the planning director, Mariano Taratutypointed out: “This stage of the work was achieved thanks to the fact that we were able to lower the playing field that allowed us those spaces where there will be new places and expansion of capacity.”

“The construction system allows us not to lose the venue because it is done on site, that’s why the fans will see how the work grows and the same will happen with the change of seats in the stalls”I consider Taratuty.

In addition, the popular ones of the stadium will be only 25 percent of the seats and will be distributed in the Sívori and Centenario headers, in the middle and lower sectors and the rest of the stadium, 75 percent, will be stalls.

new monumental.jpg

What will the second phase of the works be like?

In the second phase, which will run from the beginning of next year until July 2024the lower ring will be closed with the realization of the stalls in the Belgrano and new boxes will be built in the middle Sívori that will allow circulation throughout the ring.

What’s more, Two more floors of parking will be built, bringing the current capacity from 500 to 1,200 vehicles. and for those spectators a bridge will be built that will allow direct access from there to the box area.

From the pre-sale of these new sectors with exclusive access, the club’s treasury in charge of Andres Ballotta plans to obtain the remaining funds for this stage of the work, which will be financed entirely with genuine funds linked to the project.

On the other hand, a restaurant will be built in the area of ​​the Centenario stalls that will be open to the public all year round and will have a view into the Monumental and towards the River neighborhood on Figueroa Alcorta Avenue.

The leadership also announced that the project plans different stages of work for the sole purpose of being able to maintain the location and not having to inconvenience the member by having to leave the stadium during the works.

Meanwhile, as the work progresses, all the wooden stalls will be removed to place new anti-vandalism seats as required by law. FIFA for modern stadiums for international events.

The project must be approved on February 23 at the Extraordinary Assembly of partners, in which the ruling party has 100 of the 150 members and, it is discounted, will reach two thirds of the necessary votes.

Source: Ambito